Dorset 72 Hour Closure
Replacement of a railroad bridge over the course of 72 hours in the beginning of October.
Pre-construction
pre-cast abutment
railroad ties ready
night work
demo work
concrete curing with heaters and blankets
approach slab setting
swinging slab
swinging slab
deck set
downstream side
Some day, my doggies, work will calm down and we can run again.
Saturday, September 20, 2014
28 Day Bridge Closure
Day 1
Demo existing bridge
Day 2
Install stone fill
Days 3-5
Drive Piles
Day 6
Install precast abutments and pour rapid set concrete
Day 7
Set precast deck panels
Day 9
Placement of subbase
Day 13 - water line
Day 16 - waiting for approach slab 1
Long days and short nights, no time for Fall training even though the temps have dipped down.
Subscribe to:
Posts (Atom)
-
My amazing friend is going to swim the English Channel sometime the week of September 1st! If you'd like to follow her journey, you ca...
-
Today we went to the Adirondack Museum . It was a beautiful ride up through New York to the Adirondack's. The cost of admission was $...
-
Circles: written Jan 2010 When I was younger, I thought of the passing years as circular - the same things happening, just with a diff...