28 Day Bridge Closure
Day 1
Demo existing bridge
Day 2
Install stone fill
Days 3-5
Drive Piles
Day 6
Install precast abutments and pour rapid set concrete
Day 7
Set precast deck panels
Day 9
Placement of subbase
Day 13 - water line
Day 16 - waiting for approach slab 1
Long days and short nights, no time for Fall training even though the temps have dipped down.